The relocation checklist we actually use on aerospace jobs

A machine that took six months to prove out can be undone by a bad slinging plan. Here is what we sign off before we let the crane hook lift.

Aerospace customers do not want to hear that the machine that was cutting 30 µm TP last week now needs a week of ballbar work because a slinger caught the way covers. Here is what we tick off before the hook takes weight.

Before disconnect

  • Baseline ballbar and laser interferometer run, filed and signed.
  • Photograph the levelling pad heights and torque marks on every anchor bolt.
  • Drain and cap the coolant and hydraulic circuits. Label the caps.

On the lift

  • Lift points confirmed against the manufacturer's installation manual, not the operator's memory.
  • Slings padded at every contact with a hard edge. Way covers wrapped in shrink film, not just packing tape.
  • Spindle locked with the OEM shipping bracket. Not a bit of dowel and a prayer.

After set-down

  • Levelling to 0.02 mm/m across the bed before any electrical goes back on.
  • Warm-up run to spec, 60 minutes minimum, before geometry checks.
  • Repeat baseline ballbar and interferometer. If numbers drift more than 20% from the pre-move report, we stay on site until we know why.

Every step gets a signature and a timestamp. On MOD-adjacent work that paperwork is not overhead, it is the reason the customer sleeps.

Written by

Codeller

On the tools with King Machine Tool Services. Writes up the jobs worth learning from.

Need this kind of thinking on your machines?

Our engineers cover breakdowns, servicing, spindles, ballscrews and installs across the UK.